GMFRS – KING STREET
Project Details.
We are proud to be appointed to deliver the full demolition, asbestos removal and excavation enabling works at..
Project Duration
.
Weeks
Days
Location
STOCKPORT
Status
Completed
September 2025
Project Value
£145,000K
Recycling Rate
Number of Site Staff
Services.
Key Challenges & Solutions.
1. Demolition of the Fire Training Tower
Challenge:
-
The training tower was structurally robust, designed to withstand extreme heat and load during firefighter drills.
-
Its position within a confined site posed a risk of debris striking adjacent structures and boundary lines.
-
Standard scaffolding and protection measures would not have provided sufficient containment for falling debris.
Solution:
-
Our engineering team designed and fabricated a custom debris guard system, tailored specifically for the geometry and location of the tower.
-
The guard acted as a barrier to catch and deflect falling materials during the controlled deconstruction sequence.
-
This bespoke approach minimised vibration and impact on surrounding structures, ensured public safety, and allowed works to progress ahead of schedule.
2. Unexploded Ordnance (UXO) Risk
Challenge:
-
Historic records indicated that the site carried a potential risk of UXO contamination due to wartime activity in the Stockport area.
-
Before intrusive works could begin, there was a need to rule out any ordnance risk to protect operatives, plant, and the wider community.
Solution:
-
TOTAL engaged with specialist UXO consultants to provide a full risk assessment and guidance on mitigation measures.
-
A targeted UXO exploration survey was undertaken before groundworks commenced, ensuring the site was safe for excavation and demolition activity.
-
Our team integrated the UXO specialists’ findings into the demolition methodology, allowing works to proceed with full client and stakeholder assurance.
3. Confined Site & Restricted Access
Challenge:
-
The fire station was located in a busy part of Stockport with limited space for plant, equipment, and vehicle movement.
-
Traffic management and public interface were critical to avoid disruption and ensure safety.
Solution:
-
A carefully phased logistics plan was implemented, sequencing vehicle deliveries and waste removal to reduce congestion.
-
Use of compact, high-reach plant allowed precise deconstruction without overreaching site boundaries.
-
Temporary traffic and pedestrian management measures were coordinated with the local authority to maintain safe access routes.
4. Historic & Community Significance
Challenge:
-
King Street Fire Station carried significant heritage and community value, requiring sensitivity in its demolition.
-
Local stakeholders had concerns about noise, dust, and disruption during the works.
Solution:
-
Comprehensive dust suppression systems were deployed, including atomised mist cannons and direct-to-plant suppression lines.
-
A robust noise and vibration monitoring programme reassured both the client and local stakeholders that environmental impacts remained below thresholds.
-
Open and transparent client and community engagement was maintained throughout the project, addressing concerns proactively and demonstrating control.
5. Programme Efficiency vs. Safety
Challenge:
-
The project carried a tight programme with client requirements to meet subsequent redevelopment timelines.
-
Balancing the need for progress against strict safety requirements was critical.
Solution:
-
Sequenced demolition planning ensured high-risk elements, such as the tower, were tackled first with bespoke controls in place.
-
Additional in-house resources were mobilised free-of-charge in critical phases to ensure the programme remained ahead of schedule.
-
Daily toolbox talks, lift plans, and temporary works permits ensured safe progression without compromise.
6. Client Expectations & Satisfaction
Challenge:
-
The client required confidence that the project would not only be delivered safely and efficiently but also demonstrate innovation and industry best practice.
Solution:
-
By implementing innovative engineering (debris guard system), engaging specialist UXO expertise, and maintaining strong quality assurance processes, the project achieved recognition in industry award nominations.
-
Continuous reporting, progress photographs, and milestone updates kept the client fully informed and reassured.
-
Feedback has confirmed that the client is highly satisfied with the professionalism, communication, and outcomes of the works.