TOTAL Controlled Demolition Services was appointed to carry out the careful deconstruction and asbestos removal works of the Old Stores Building at Carrington. The objective was to clear the site safely and efficiently to facilitate the next phase of redevelopment, while protecting surrounding infrastructure — most notably, a critical substation asset located in extremely close proximity to the demolition footprint.
This project was part of a wider site regeneration programme, requiring precise coordination and a controlled demolition sequence to ensure no disruption to ongoing services or existing live infrastructure.
Full pre-demolition audit including identification of salvageable materials and environmental considerations
Soft strip works including removal of non-structural elements, fixtures, and redundant M&E
Deconstruction of the main structural frame, walls, and roof using a carefully planned sequence to mitigate risk to adjacent assets
Segregation and removal of waste in line with our recycling strategy, maximising recovery and minimising landfill
Final site clearance to development-ready standards